Huntingdonshire District Council
Local plans
Contents
Huntingdonshire Local Plan 2046
Planning policy url
Plan period
2021-2046
Housing numbers
32,200
Housing requirement total
View source document
Notes
Policy LP 1
How much development do we expect?
To meet Huntingdonshire's future housing needs in the period 2021 to 2046 provision will be made for at
least 32,200 new homes across a range of tenures.
Between 2021/22 and 2024/25 4,402 homes were counted as completed within the government's standard
methodology inputs.
From 2025/26 to 2045/46 the standard method requirement is 1,237 homes per year, totalling 25,977. An
uplift of just over 5% is applied to allow some flexibility resulting in a total requirement of 27,300.
The delivery of these will be phased through a stepped approach to the housing trajectory reflecting the need
for infrastructure provision to support new homes. Homes are expected to be phased as:
at least 5,250 homes in 2025/26 to 2029/30 with an annual average of 1,050 homes
at least 6,250 homes in 2030/31 to 2034/35 with an annual average of 1,250 homes
at least 16,300 homes in 2035/36 to 2045/46 with an annual average of 1,482 homes
PINS data
Local development framework number: 2477
published
16 Sep 2026
PINS Timeline
| published | 16 Sep 2026 |
|---|
Huntingdonshire's Local Plan to 2036
Planning policy url
Plan period
2011-2036
Housing numbers
20,100
Housing requirement total
View source document
PINS data
Local development framework number: 1882
adopted
15 May 2019
PINS Timeline
| published | 18 Dec 2017 |
|---|---|
| submitted | 28 Mar 2018 |
| sound | 29 Apr 2019 |